Guide to RIBA domestic and concise building contracts 2018 / Sarah Lupton.
2018
Formats
Format | |
---|---|
BibTeX | |
MARCXML | |
TextMARC | |
MARC | |
DublinCore | |
EndNote | |
NLM | |
RefWorks | |
RIS |
Items
Details
Author
Title
Guide to RIBA domestic and concise building contracts 2018 / Sarah Lupton.
Imprint
London : RIBA Publishing, 2018.
Description
1 online resource
Formatted Contents Note
Cover; Title; Copyright; Foreword; About the author; Contents; About this Guide; 1 Introduction; Features of the RIBA Building Contracts; Suitability for different procurement routes; Differences between the concise and domestic contracts; Use by domestic and commercial clients; Use by public bodies; Changes to the forms since the previous editions; Comparison with other contracts; 2 Forming the contract; Tendering; Implications of the Consumer Rights Act 2015; Tendering procedures; Information that must be included in tender documents; Pre-contract negotiations
Preparing and executing the contract packageInterpreting the contract and resolving inconsistencies; Definitions; Priority of contract documents; Inconsistencies, errors or omissions; 3 Roles and management systems; Role of the contract administrator; Role of the client; Client acting as contract administrator; Role of the contractor; Completing the works; Contractor's design obligation; Contractor's design liability; Contractor's obligations in respect of subcontracted work; Compliance with statute/health and safety legislation; Management systems; Pre-start meeting; Progress meetings
Risk register4 Project progress; The site: possession; Starting the work; Completion in sections; The contractor's programme; Content of programme; Progress; Updated programmes; Finishing the work; Delay; Revisions to the contract completion date; Applying for a revision of time; Assessment of an application; Final assessment of revisions of time; 5 Control of the works; Control of day-to-day activities; Contractor's representative; Responsibility for subcontractors; Principal designer; Flow of information; Information to be provided by the contract administrator
Information to be provided by the contractorInspection and tests; Inspection; Testing and defective work; Contractor administrator's instructions; Delivery of instructions; Procedure following an instruction; 6 Payment and certification; The contract price; Adjustments to the contract price; Certification and payment; Advanced payment; Interim payments
monthly certification; Interim payments
milestone payments; Interim payments
payment on practical completion; Payment of interim payments; Contractor's remedy if no certificate issued; Contractor's remedies if certificate not paid
7 Practical completion, completion and post-completionPractical completion; Consequences of practical completion; Use/occupation before practical completion; Non-completion; The defects fixing period; Payments following practical completion; Final contract price and payment; Conclusiveness; 8 Insurance; Liability; Indemnity; Insurance; Professional indemnity insurance; 9 Termination; Termination by the client; Abandoning the works; Failing to proceed regularly and diligently; Failing to comply with instructions; Material breach of contract; Procedure for terminating
Preparing and executing the contract packageInterpreting the contract and resolving inconsistencies; Definitions; Priority of contract documents; Inconsistencies, errors or omissions; 3 Roles and management systems; Role of the contract administrator; Role of the client; Client acting as contract administrator; Role of the contractor; Completing the works; Contractor's design obligation; Contractor's design liability; Contractor's obligations in respect of subcontracted work; Compliance with statute/health and safety legislation; Management systems; Pre-start meeting; Progress meetings
Risk register4 Project progress; The site: possession; Starting the work; Completion in sections; The contractor's programme; Content of programme; Progress; Updated programmes; Finishing the work; Delay; Revisions to the contract completion date; Applying for a revision of time; Assessment of an application; Final assessment of revisions of time; 5 Control of the works; Control of day-to-day activities; Contractor's representative; Responsibility for subcontractors; Principal designer; Flow of information; Information to be provided by the contract administrator
Information to be provided by the contractorInspection and tests; Inspection; Testing and defective work; Contractor administrator's instructions; Delivery of instructions; Procedure following an instruction; 6 Payment and certification; The contract price; Adjustments to the contract price; Certification and payment; Advanced payment; Interim payments
monthly certification; Interim payments
milestone payments; Interim payments
payment on practical completion; Payment of interim payments; Contractor's remedy if no certificate issued; Contractor's remedies if certificate not paid
7 Practical completion, completion and post-completionPractical completion; Consequences of practical completion; Use/occupation before practical completion; Non-completion; The defects fixing period; Payments following practical completion; Final contract price and payment; Conclusiveness; 8 Insurance; Liability; Indemnity; Insurance; Professional indemnity insurance; 9 Termination; Termination by the client; Abandoning the works; Failing to proceed regularly and diligently; Failing to comply with instructions; Material breach of contract; Procedure for terminating
Summary
This latest title from the author provides comprehensive guidance to RIBA's two updated building contracts: the RIBA Domestic Building Contract 2018 and the RIBA Concise Building Contract 2018. Introducing the contracts' features and benefits and covering all aspects of their use, from choosing and forming the right one for your project to guiding the parties through all its various stages, the Guide has been expanded with increased assistance on choice of form, tendering and contract formation.Additional detail on role and liabilities of contract administrator has been added, along with a newsection on practical completion and completion, including certification. Assuming no current knowledge of the law or contract administration, this acts as a standalone guide for new users of the RIBA contracts, as well as a valuable update for previous users. It is an ideal companion for anybody using the latest building contracts.
Source of Description
OCLC-licensed vendor bibliographic record.
Location
www
Linked Resources
Alternate Title
Taylor & Francis Online
Language
English
ISBN
9780429345906 (electronic book)
0429345909 (electronic book)
9781000702095 (electronic book : Mobipocket)
100070209X (electronic book : Mobipocket)
9781000702323 (electronic book : EPUB)
1000702324 (electronic book : EPUB)
9781000701869 (electronic book : PDF)
1000701867 (electronic book : PDF)
9781859468630
1859468632
0429345909 (electronic book)
9781000702095 (electronic book : Mobipocket)
100070209X (electronic book : Mobipocket)
9781000702323 (electronic book : EPUB)
1000702324 (electronic book : EPUB)
9781000701869 (electronic book : PDF)
1000701867 (electronic book : PDF)
9781859468630
1859468632
Record Appears in